CAT excavator over two new precast manholes on Kingston Road
← All projects
In progressMunicipal sewer separationVancouver (UEL)

Western Crescent & Kingston Road Sewer Separation

Municipal sewer separation · Vancouver (UEL) · 2026

NSC built
Client
University Endowment Lands
Contractor
Neil Smith Construction (prime)
Started
May 2026
Status
Final restoration, fall 2026

About the project

Separating the combined sewer on Western Crescent and Kingston Road into new sanitary and storm systems for the University Endowment Lands.

The existing combined sewer carried sanitary flow and stormwater in one pipe. We replaced it with two new systems laid side by side: a sanitary main and a storm main, each with its own manholes, service connections and catch basins.

The work ran through a quiet residential street with homes on both sides. Every property stayed connected through the job. New services were installed ahead of time and transferred over once the new mains were tested.

We hold the prime contract and deliver the excavation, pipe, manholes, water services and concrete, with paving placed by our asphalt subcontractor.

12new precast manholes
15properties reconnected
7new catch basins
250 to 450 mmsanitary and storm mains

How the job ran

  1. May 2026Notice to proceed, mobilization, locates and sampling
  2. May to AugSanitary and storm mains, manholes and services
  3. Jul to AugWater services, hydrant, testing and tie-ins
  4. Aug to SepService transfers, CCTV and pressure tests
  5. Fall 2026Concrete, paving and landscape restoration